Isbern acknowledges that a good option for a tri-mode Class 319 would have been London Overground, but with the Gospel Oak-Barking route now being electrified that particular customer has been eliminated.
Most of Porterbrook’s work to date has focused on the Class 319 Flex, but the concept could be deployed on other fleets. Isbern says the Marshlink route from Ashford, deep in third-rail territory, is an option - it only needs DC plus diesel power.
“The Flex concept could be deployed on fleets such as Electrostar and displace DMUs for use in other parts of the country,” he says.
Simpson says there is no Flex ready yet, but work has begun. And timescales for the project are impressive.
She explains: “When production is up and running, each ‘319’ will take four to six weeks to convert. The rafts will be built in advance and simply be bolted on to the train during conversion at works, thus minimising downtime.
“The design of the control system is largely developed and an Ethernet backbone will be used to monitor output and balance loading between the two engine rafts. The physical modifications needed are relatively straightforward and are largely limited to the driving vehicles - fitting the new engine/alternator raft, some new control technology and some minor relocation of existing equipment. It is a modular concept and it is cost-effective as a result.”
She admits that while the first train will take longer, as per all usual rebuilds and refurbishments, the timescales will improve dramatically when the production is up and running. Initially eight Class 319s will be converted, and form part of the Northern fleet of 32.
“The first four could enter traffic in December 2017,” Isbern tells RAIL.
The ‘319s’ to be converted have been identified by painted number already. Initially they will all be ‘319/4s’, but any of the four sub-classes could be used. Isbern says it makes sense to use the ‘319/4s’ first as they are the most readily available. All of Northern’s Class 319s in traffic currently are ‘319/3s’, but ‘319/4’ Flex units will be able to couple and work in multiple with any ‘319’ sub-fleet.
Northern will be responsible for maintenance. Depending on their diesel utilisation, Isbern is not convinced that the new engine rafts will need overhauling during the lifetime of the Northern franchise (which began in April 2016 and will run for nine years, plus a one-year option). This means that trains introduced in December 2017 could run for nine years without the need to visit works for major engine attention.
Isbern adds: “We don’t know yet which exact routes Northern will use the Flex units on. We know they outperform a ‘150’ on a number of different routes and diagrams, and will certainly outperform a Pacer. We are working closely with Northern on approvals for their selected routes.”
Certainly routes in the North West where new OLE is being erected, or where journeys are mostly under the wires, are likely future candidates.
Simpson adds: “The costs benefit model is interesting. Under the wires the pantograph can go up and the engine is switched off. In diesel mode, the engine is running at maximum efficiency through the existing traction equipment and is as fuel-efficient as a new DMU. Overall, you end up with a much more efficient train compared with running diesels under the wires.
“Track access is marginally more than an existing ‘319’, but comparable to a mid-life DMU. It is roughly the same weight as two ‘150s’ and should give a comparable track access charge. The fuel savings of only running diesel engines when you need them, and running them at a maximum efficiency, give a significant total energy cost saving when compared with a pure DMU option.”
Simpson explains that when running as an EMU the top speed for Flex is 100mph. She adds that, being conservative, when running on diesel it’s likely to be around 91mph-92mph. “Really detailed point-to-point analysis shows what it does well, and which routes and journeys will deliver the biggest benefits to operators,” she tells RAIL.
So how far has Porterbrook got?
“We have done all the concept design work, gauging work, and weight analysis, structural modelling, braking, journey time and performance calculations have all been completed,” says Isbern.
“Detailed design is now well under way. We know the suppliers we’ll use, and it is about getting into the details. The materials are ordered - we are really cracking on with it.”
Porterbrook and Northern have yet to decide on an interior, but discussions are in progress.
One unit has moved to Loughborough (319427), but this is not one of the eight destined for Northern. Instead, it will be deployed for dimensional analysis. Only so much can be planned on paper and computers, and this will enable the various teams to evaluate the train and ensure everything fits.
Isbern reveals that when the first production unit is released from Loughborough, it will move to Allerton depot, where Northern maintains its other ‘319s’. Refuelling will be no problem, given that this is also a DMU depot.
The predicted reliability of the units is measured in miles per technical incident (MTIN) and is not too different from a ‘319’ with a target level of 20,000 miles per incident, says Isbern.
He is keen that Flex is marketed to other areas beyond Northern. The ‘319’ fleet is in good condition and all of the units selected for Flex are also already PRM-TSI (Persons of Reduced Mobility - Technical Specifications for Interoperability) compliant, which means they can be used beyond January 1 2020. “We can see Flex units operating beyond 2025,” says Isbern.
This is a project that seems the right option for right now. The nationwide shortage of DMUs has even been debated in the Commons by Rail Minister Paul Maynard in recent weeks. This low-cost alternative to brand new trains offers train operating companies the opportunity to introduce refurbished bi-mode trains using an asset that has plenty of life in it. It’s surely a win-win for all those involved?
Comment as guest
Comments
James Miller - 14/03/2017 14:34
I have been sent an early copy of the brochure by Porterbrook. Reading it, you get the idea that it is serious and very professional project. I was in Blackburn over the weekend and travelled to Buxton and Clitheroe. Those lines are stiff and there is a lot of housing and other develoments going on. I have done a few calculations and reckon the trains could work Clitheroe to Buxton in a reasonable time, when Bolton to Hazel Grove is fully electrified. Arrange the diagrams correctly and I reckon Manchester to Buxton and Blackburn could be two tph with one tph to Hellifield and four tph to Hazel Grove. Hellifield to Buxton would be an ideal tourist route and link the S&C to Manchester. It would even be run by electric trains with a good heritage. But please, do a decent interior, like South West Trains did for the 455, which are of a similar age.
Reply as guest
Rob Lewis - 17/03/2017 12:29
These trains would be great for the Reading - Gatwick route, until they fill in the gaps in the 3rd rail.
Reply as guest
BigTone - 01/04/2017 19:34
Agreed, also all the other branches down there. Allow the diesels to be cascaded to where they are needed.
Reply as guest
AndrewG1989 - 19/03/2017 21:52
I think that the Class 319's that are to be cascaded from Thameslink to Northern will benefit the need of introducing not just older rolling stock trains to replace the Class 144 Pacers but also to fit in new diesel engines onto the Class 319's so that not only they be EMUs but also to be reclassified as EDMU (Bi-Mode) flex rolling stock trains that can operate on both AC 25kv Overhead electrified lines but also on non-electrified lines in the North of England. Also Northern are to order the new Class 331's and Class 195's for other routes and possibly to cascade the Class 333's for the Leeds-Doncaster route as well working on Leeds suburban lines along with the Class 321/9's & Class 322's that are still currently operating on the Leeds-Doncaster service.
Reply as guest
FrankH - 20/03/2017 09:09
Once the Euxton Junction - Manchester OLE is complete they will take over most of the Blackpool North - Manchester- Hazel grove and perhaps Buxton workings also Southport - Manchester Airport and Hazel Grove but not the Victoria runs for Northern. Trans Pennine Express could use them on Blackpool - Manchester Airport workings. The Manchester/Preston - Windermere workings are another prime example. The Carnforth-Barrow section of the Manchester runs at 29 miles on diesel engines is another candidate. The North West is a breeding ground for this type of dual energy unit with lots of potential.
Reply as guest